Buying into a big township is a trust game. You want proof that work is moving, not just glossy renders. This page tracks Nambiar District 25 on Sarjapur Road the way a buyer would: what is happening on site, how it matches filings, and what the next 3 to 6 months look like. You will see clean steps you can verify yourself and a simple snapshot for quick decisions. Keywords like Nambiar Builders, Nambiar Group, Nambiar projects, nambiar district 25 construction status today, and nambiar district 25 construction status Bangalore are used naturally so the page reads well and ranks well.


Phase 1 has moved past pure earthwork. Raft slabs are done in pockets, rebar is stacked near core walls, and shuttering teams are cycling through early vertical pours. In plain words, foundation is active and the first lifts of the super structure are visible on select towers. Expect some blocks still finishing pits while others rise. That mixed picture is normal in a 60 plus acre township.

Month & year What moved Notes you can check
Jan 2025 Phase 1 excavation began Breaking ground and pit marking across first blocks
Feb 2025 Bulk excavation across multiple pits Support walls and ramp edges visible on site walks
Apr 2025 Raft concreting started on early towers First major structural pours, crew sizes ramp up
May 2025 Foundation widening across blocks More rebar cages, pump lines, curing mats on slabs
Jun–Aug 2025 Construction in full swing Repeat pour cycles, crane activity, steady manpower
  • Banks release funds against real stages. A live site helps disbursements stay smooth.
  • You can match your tower's stage to the demand note and pay only against visible progress.
  • For buyers comparing micro markets, this is a real build, not a paper launch.

Pro tip for site visits: go in the morning. You will usually catch pours, reinforcement checks, and crane cycles before midday heat slows crews.


  • Registered with the regulator.
  • Outer possession band communicated as 2028 to 2030, with tower wise variation.
  • Your action: note your exact tower name and stack plan. Open the latest filing and read the schedule of completion for that tower, not just the overall phase.
  • Pre launch communications are live. Filings and approvals are targeted in the 2025 window, with mobilization planned to follow.
  • Your action: before booking, confirm the registration entry and collect the registration number on your application and demand notes.
  1. Search the regulator site by project name or Nambiar Builders.
  2. Open the certificate. Screenshot validity dates, survey numbers, and tower list.
  3. Review uploads for plans, progress, and any addenda.
  4. Ask your banker to map disbursement stages to the same schedule. If a demand note does not match the stage, hold the payment.

This simple routine keeps you aligned with filings and removes the guesswork that brochures often create.


Large Nambiar projects run many fronts at once. Tower 3 may be at raft level while Towers 1 and 2 climb. Always anchor your decision to your tower's live position.

Request the last two photo sets for your tower, with dates printed or watermarked. The sequence should show reinforcement checks, formwork closing, and the pour. Pair those dates with your demand notes. If you live away, ask for a short video that starts with tower signage, then pans to the active slab. That removes ambiguity.

  • Earthwork closed: ramps gone, edges backfilled and compacted.
  • Raft and footings: dense rebar mats, pump lines, curing sheets.
  • Vertical start: columns or shear walls up, formwork panels stacked nearby, tower crane cycling faster.
  • Podium and MEP: sleeves in slabs, shaft openings, conduits laid. Civil and services teams overlap here.
  • Every demand note carries the phase or tower reference and the registration number.
  • Your allotment letter names the tower and the unit stack.
  • The bank's disbursement stage matches a stage you can see or verify on camera.

These habits work across Sarjapur Road and protect you from marketing noise.

To set expectations, here is a clean flow for a township like Nambiar District 25. This blends the communicated build plan with how big sites actually run.

Work stage Typical window What you will notice
Sub structure Jan 2025 to mid 2026 Pits, rafts, footings, retaining walls, early basements
Super structure Late 2025 to late 2027 Columns, shear walls, floor slabs rising in cycles
Finishing and services 2026 to 2029 Masonry, plaster, MEP, facade, lifts, fire systems
Handovers 2028 to 2030 Tower wise possession based on sequencing
Work stage Typical window What you will notice
Sub structure Late 2025 to 2027 Mobilization after approvals, parallel pits open
Super structure 2026 to 2028 Regular climb once shuttering sets stabilize
Finishing and services 2027 to 2030 Interior fit outs, testing, external works
Handovers Late 2029 to 2030 Sequenced by tower and amenities readiness
  • More tower cores climbing in Phase 1 as shuttering sets multiply.
  • First podium slabs and early MEP shaft work on the leading blocks.
  • Quarterly filing updates reflecting structural progress, then services.
  • Clearer alignment between demand notes and on ground milestones.

If you plan to lock a home loan, this sub structure to super structure window is usually where progress becomes very visible and payment schedules are easier to track.

Tower Current zone Buyer takeaway
Tower 1 Foundation and vertical start in pockets Expect steady floor cycles once shuttering settles
Tower 2 Foundation widening and prep for verticals Watch for first slab pour and rebar checks
Tower 3 Raft completed and early verticals visible Good reference tower to judge pace and crews

You are not chasing perfect renders. You are matching dates, photos, and filings. Keep checks tower wise, insist on dated proof, and release payments only against a stage you can verify. That is how you stay ahead of the usual sales talk with Nambiar Builders and the Nambiar Group, and that is how you buy confidently at Nambiar District 25.

Nambiar District 25 Blog


Featured Image of Nambiar District 25 Apartments
Featured Image of Nambiar District 25 Construction Status
Featured Image of Nambiar District 25 RERA Approval

Featured Image of Nambiar District 25 Muthanallur Cross
Featured Image of Nambiar District 25 Payment Plan
Featured Image of Nambiar Bellezea

Featured Image of Nambiar Ellegenza
Featured Image of Best Causes To Buy Nambiar Property At East Bangalore
Featured Image of Best Ongoing Property In Sarjapur Road


Disclaimer : The content is for information purposes only and does not constitute an offer to avail of any service. Prices mentioned are subject to change without notice and properties mentioned are subject to availability. Images for representation purposes only. This is the official website of authorized marketing partner. We may share data with RERA registered brokers/companies for further processing. We may also send updates to the mobile number/email id registered with us. All Rights Reserved.

Enquiry
Enquire Now